Start before verification is complete

The law lets a firm start a service before a customer's identity checks are finished, on narrow conditions. This page records that decision on the engagement and keeps the deadline visible. Any staff member working the engagement can record it.

Why this matters​

The law lets a firm start a service before a customer's due diligence is finished only where strict conditions are met and the delay is recorded. The firm has to be satisfied that starting now is essential and that the added risk is low, and it has to finish the checks by the deadline the Rules set. See Customer due diligence.

Before you start​

The engagement must exist and the customer must be on it, with their structure committed and their screening run and decided. Everything except verification has to be done first.

Your approved program must allow it. Where the program does not, the button is not offered.

Steps​

  1. Open the engagement and find the customer who is not verified.
  2. Choose Start before verification is complete.
  3. Under Which rule?, choose the basis the situation falls under:
    • the general delay, 20 business days after the service starts;
    • the buyer of a real estate transaction, or of work on a transaction, where the earlier of 28 days after exchange or 3 days before the agreed settlement applies;
    • the other side of a sale, on the same earlier-of date.
  4. Where you chose the buyer or the other side, enter the Exchange date and the Settlement date (as agreed).
  5. Record Why starting now is essential, which is the determination that delaying would interrupt the ordinary course of business.
  6. Record Why the added risk is low, and how you manage it.
  7. Check the date shown as Due. Choose Record and start.
The delayed-start dialog: the rule that applies, what must be done first (here, screening still to decide), the dates, and the two determinations to record.The delayed-start dialog: the rule that applies, what must be done first (here, screening still to decide), the dates, and the two determinations to record.
The delayed-start dialog: the rule that applies, what must be done first (here, screening still to decide), the dates, and the two determinations to record.

If an item is still outstanding, the dialog lists it under Not yet: first and will not save. The list names the ownership structure, screening for everyone who must be screened, and any possible match left to decide.

What Duely checks​

  • Screening is never deferred. Everyone who must be screened is screened and every possible match decided before the delay is recorded.
  • The ownership structure must be committed first, where the customer type has one.
  • Both determinations are required, and both are kept with the person who made them and the time.
  • The engagement and the customer both carry the restriction: nothing is released for that customer while verification is pending. Holding money on deposit is not a release.
  • The due date is set from the basis chosen. When it passes with the customer still unverified, no further step is taken for them on the engagement and the AMLCO is told.
  • A customer added after approval whose checks are not done also stops releases for that customer until the checks are done or a delayed start is recorded.

What happens next​

The customer's profile shows Verification pending with the date, and the engagement carries the banner. Finish the identity checks on Identity checks, then continue with Approvals and Release money or property.

The engagement banner for a delayed start, naming the customer and the date verification is due.The engagement banner for a delayed start, naming the customer and the date verification is due.
The engagement banner for a delayed start, naming the customer and the date verification is due.

The law​

Last updated: 4 October 2026

These pages are general information about the Duely product and the AML/CTF obligations it supports. They are not legal advice and do not cover your firm's particular circumstances.